# STELCOR® DDM For 8-Story Building in Brooklyn

 June 29th, 2016

 1 min read

 By [Bruce Stroyer](https://www.idealfoundationsystems.com/blog/author/bruce-stroyer)

![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/211-McGuinness-STELCOR-Case-Study-1-150x150-1.jpg?width=150&height=150&name=211-McGuinness-STELCOR-Case-Study-1-150x150-1.jpg)

**OVERVIEW:**  
An 8-story mixed use building designed by Gene Kaufman is currently going up at 211 McGuinness Blvd. in the Greenpoint neighborhood of Brooklyn. The anticipated install rate of the originally specified micropile was 2 piles per day. A total of 340 drilled-in displacement piles were installed on this project.

 

**CHALLENGE:**  
The greatest challenge with this project was the high water table and the significant costs that would be associated with excessive dewatering. The tops of the piles were 4’ to 6’ below the water table. Before the[ STELCOR DDM ](https://www.idealfoundationsystems.com/stelcor-products/)(Drilled-In Displacement Pile) was introduced as an alternate, there were two options for pile installation; excessive dewatering or install the pile, excavate, and cut-off.

 

**SOLUTION:**  
Using the below-grade drive tool engineering and manufactured by IDEAL, the need for dewatering was eliminated. The 340 STELCOR DDM were installed to 120,000 ft. lbs. using a Digga MD160 drive motor. The piles were installed at a rate of 10 per day as opposed to the anticipated 2 piles per day with the originally specified micropile. The elimination of dewatering costs and the accelerated install times resulted in significant benefits to all parties involved.

[View the full case study that includes soil borings, load tests, etc. HERE.](https://www.idealfoundationsystems.com/hubfs/CASE%20STUDY/211%20McGuinness%20-%20STELCOR%20CASE%20STUDY.pdf)

[See how STELCOR Drilled-In Displacement Micropiles can save your project.](https://www.idealfoundationsystems.com/stelcor-products/)

OWNER:  
Stellar Management  
New York, NY

ARCHITECT:  
Gene Kaufman Architect PC  
New York, NY

GENERAL CONTRACTOR:  
Britt Realty Construction  
Brooklyn, NY

STRUCTURAL ENGINEER:  
Gene Kaufman Architect PC  
New York, NY

GEOTECHNICAL ENGINEER:  
AECOM  
New York, NY  
and  
Geotechnical Engineering Services, P.C.  
Elmsford, New York

INSTALLER:  
Champ Construction Corp.  
Hempstead, NY

LOADS:  
150 tons allowable compression  
75 tons allowable tension  
1 ton allowable lateral

ANTICIPATED TEST LOAD: 300 tons  
ACTUAL TEST LOAD: 300 tons

SPECIFICATIONS:  
7” pile shaft  
.498” W.T. 80 ksi  
16” corrugated grout column  
18” tip or drive plate  
39.8 ft. bond length  
25 psi acheived bond

 Topics:

[ Case Study ](https://www.idealfoundationsystems.com/blog/topic/case-study)

[ Drilled-In Displacement Piles (DDM) ](https://www.idealfoundationsystems.com/blog/topic/drilled-in-displacement-piles-ddm)

[ STELCOR ](https://www.idealfoundationsystems.com/blog/topic/stelcor)

 Don't forget to share this post:

<https://www.facebook.com/sharer/sharer.php?u=https://www.idealfoundationsystems.com/blog/340-stelcor-micropiles-new-8-story-building-brooklyn-ny> <https://www.linkedin.com/shareArticle?url=https://www.idealfoundationsystems.com/blog/340-stelcor-micropiles-new-8-story-building-brooklyn-ny&title=STELCOR%C2%AE+DDM+For+8-Story+Building+in+Brooklyn&summary=340+Stelcor+Micropiles+have+been+set+into+the+ground+to+support+a+new+8-story+building+in+Brooklyn%2C+New+York.+See+our+progress+here%21> <https://twitter.com/intent/tweet?text=STELCOR%C2%AE+DDM+For+8-Story+Building+in+Brooklyn&url=https://www.idealfoundationsystems.com/blog/340-stelcor-micropiles-new-8-story-building-brooklyn-ny> <https://pinterest.com/pin/create/button/?url=https://www.idealfoundationsystems.com/blog/340-stelcor-micropiles-new-8-story-building-brooklyn-ny&media=https://47216011.fs1.hubspotusercontent-na1.net/hubfs/47216011/Imported_Blog_Media/211-McGuinness-STELCOR-Case-Study-1-150x150-1.jpg&description=340+Stelcor+Micropiles+have+been+set+into+the+ground+to+support+a+new+8-story+building+in+Brooklyn%2C+New+York.+See+our+progress+here%21>

## Related Articles

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Baltic%20St_.png?width=713&height=401&name=Baltic%20St_.png)

### STELCOR Supports a Complex Development Site in Brooklyn’s Gowanus Neighborhood

 May 18th, 2026|1 min read 

](https://www.idealfoundationsystems.com/blog/stelcor-supports-a-complex-development-site-in-brooklyns-gowanus-neighborhood)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/16-777x246.jpg?width=777&height=246&name=16-777x246.jpg)

### STELCOR Piles Installed Adjacent to Elevated MTA for Lorimer House Project

 May 18th, 2026|1 min read 

](https://www.idealfoundationsystems.com/blog/stelcor-piles-installed-adjacent-to-elevated-mta-for-lorimer-house-project)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/image-webp.webp?width=1350&height=900&name=image-webp.webp)

### NYC - 272 STELCOR Piles Installed for a 14-Story Development in Gowanus

 August 1st, 2025|1 min read 

](https://www.idealfoundationsystems.com/blog/nyc-272-stelcor-piles-installed-for-a-14-story-development-in-gowanus)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/86%20DELANCEY%20web(16)--jpg.jpeg?width=720&height=471&name=86%20DELANCEY%20web(16)--jpg.jpeg)

### NYC - 112 STELCOR® Piles to 30' for a 12-Story Mixed-Use Rental Building

 June 23rd, 2025|1 min read 

](https://www.idealfoundationsystems.com/blog/nyc-112-stelcor-piles-to-30-for-a-12-story-mixed-use-rental-building)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/INSTALL-SNIP-2-WEB.jpg?width=720&height=404&name=INSTALL-SNIP-2-WEB.jpg)

### 5.5″ HELICAL PILES FOR A HOSPITAL PARKING GARAGE RETROFIT

 December 28th, 2022|1 min read 

](https://www.idealfoundationsystems.com/blog/5-5-helical-piles-for-a-parking-garage-retrofit)

[![STELCOR® DDMS TOUCHING DOWN AT JFK AIRPORT](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/20220617_140517-WEB-scaled.jpg?width=2560&height=1920&name=20220617_140517-WEB-scaled.jpg)

### STELCOR® DDMS TOUCHING DOWN AT JFK AIRPORT

 October 31st, 2022|1 min read 

](https://www.idealfoundationsystems.com/blog/stelcor-at-jfk)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/install-gap-2.jpg?width=2400&height=1354&name=install-gap-2.jpg)

### 42 STELCOR® DDMS FOR WIND TURBINES IN CALIFORNIA

 July 25th, 2022|1 min read 

](https://www.idealfoundationsystems.com/blog/42-stelcor-ddms-for-wind-turbines-in-california)

[![FLYING EXCAVATORS AND STELCOR DDM’S AT A PAPER MILL IN DULUTH, MN](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/duluth-3-web-1.jpg?width=900&height=505&name=duluth-3-web-1.jpg)

### FLYING EXCAVATORS AND STELCOR DDM’S AT A PAPER MILL IN DULUTH, MN

 June 29th, 2022|1 min read 

](https://www.idealfoundationsystems.com/blog/flying-excavators-and-stelcor-ddms-at-a-paper-mill-in-duluth-mn)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/20210611_100954-WEB.jpg?width=2048&height=1536&name=20210611_100954-WEB.jpg)

### 93 STELCOR DDM’S INSTALLED FOR A 7-STORY HOSPITAL ADDITION

 March 3rd, 2022|1 min read 

](https://www.idealfoundationsystems.com/blog/93-stelcor-ddms-installed-for-a-7-story-hospital-addition)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/DSC00162-1.jpg?width=872&height=583&name=DSC00162-1.jpg)

### NYC – 75 STELCOR Piles for 8-Story Cantilevered Condos

 July 30th, 2021|1 min read 

](https://www.idealfoundationsystems.com/blog/nyc-75-stelcor-piles-8-story-cantilevered-condos)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/DC-SEWER-2-150x150-1-1.jpg?width=150&height=150&name=DC-SEWER-2-150x150-1-1.jpg)

### Keeping it Clean in Washington D.C. With STELCOR

 February 11th, 2021|1 min read 

](https://www.idealfoundationsystems.com/blog/keeping-clean-washington-d-c-stelcor)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/PATH-WEB-1.jpg?width=436&height=325&name=PATH-WEB-1.jpg)

### On the beaten PATH: More IDEAL Helical Piles In The NY/NJ Subway Stations

 October 8th, 2020|1 min read 

](https://www.idealfoundationsystems.com/blog/on-the-beaten-path-more-ideal-helical-piles-in-the-ny-nj-subway-stations)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/FNC-rendering-web-150x150-1.png?width=150&height=150&name=FNC-rendering-web-150x150-1.png)

### STELCOR For The First National Center

 August 10th, 2020|1 min read 

](https://www.idealfoundationsystems.com/blog/stelcor-for-the-first-national-center)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/CHSB-26.jpg?width=900&height=506&name=CHSB-26.jpg)

### Helical Pile Foundations for COVID-19 Field Hospitals in New York

 May 1st, 2020|1 min read 

](https://www.idealfoundationsystems.com/blog/helical-pile-foundations-for-covid-19-field-hospitals-in-new-york)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/302-east-2nd-street-exterior-rendering.jpg?width=736&height=401&name=302-east-2nd-street-exterior-rendering.jpg)

### NYC – East Village Homes See STELCOR Savings

 January 21st, 2020|1 min read 

](https://www.idealfoundationsystems.com/blog/east-village-homes)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/IMG_1908-resize.jpg?width=640&height=480&name=IMG_1908-resize.jpg)

### IDEAL Helical Piles at the naval academy

 September 17th, 2019|1 min read 

](https://www.idealfoundationsystems.com/blog/ideal-helical-piles-at-naval-academy)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/lincoln-terminal-helical-piles-night.jpg?width=576&height=324&name=lincoln-terminal-helical-piles-night.jpg)

### 1,321 Helical Pipe Piles for Lincoln Terminal in Natchez

 September 13th, 2019|1 min read 

](https://www.idealfoundationsystems.com/blog/1321-helical-pipe-piles-for-lincoln-terminal-in-natchez)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/NYHC-awards_DraperHall_image4-910x1024-910x1024-1.jpg?width=910&height=1024&name=NYHC-awards_DraperHall_image4-910x1024-910x1024-1.jpg)

### 295 STELCOR® DDM for the new 16-Story Gilbert in NYC

 March 9th, 2019|1 min read 

](https://www.idealfoundationsystems.com/blog/its-gonna-be-a-gilbert)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/Blackspring-Ridge-Wind-Project-Vickars-Image-7.jpg?width=640&height=360&name=Blackspring-Ridge-Wind-Project-Vickars-Image-7.jpg)

### 13.375″ Helical Pipe Piles For Western Canadas Largest Wind Project

 December 14th, 2018|1 min read 

](https://www.idealfoundationsystems.com/blog/13-375-helical-pipe-piles-300-megawatt-solar-project-alberta)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/86-DELANCEY-5.jpg?width=600&height=800&name=86-DELANCEY-5.jpg)

### A Boring Story – How to Save 6 Weeks, 50 Foot, and $500,000.00

 August 3rd, 2018|1 min read 

](https://www.idealfoundationsystems.com/blog/1972-2)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/draper2.jpg?width=640&height=480&name=draper2.jpg)

### NYC – 126 STELCOR® Piles to 75’ for a 14-Story Addition at Draper Hall

 May 1st, 2018|1 min read 

](https://www.idealfoundationsystems.com/blog/nyc-126-stelcor-micropiles-to-75-for-a-14-story-addition-at-draper-hall)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/Spiegel-Community-Center-Helical-Piles2.png?width=872&height=583&name=Spiegel-Community-Center-Helical-Piles2.png)

### 7″ Helical Pile Underpinning For A 100-Year-Old Community Center

 April 4th, 2018|1 min read 

](https://www.idealfoundationsystems.com/blog/7-helical-pile-underpinning-100-year-old-community-center)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/DSC01761-web.jpg?width=872&height=583&name=DSC01761-web.jpg)

### Cornell University – STELCOR® DDM for Increased Column Loading In The Historic Rand Hall

 March 21st, 2018|1 min read 

](https://www.idealfoundationsystems.com/blog/cornell-university-stelcor-ddm-increased-column-loading-historic-rand-hall)

[![](https://www.idealfoundationsystems.com/hs-fs/hubfs/Imported_Blog_Media/DC-SEWER-2-1024x576-2.jpg?width=1024&height=576&name=DC-SEWER-2-1024x576-2.jpg)

### Keeping it Clean in Washington D.C. With STELCOR

 February 2nd, 2018|1 min read 

](https://www.idealfoundationsystems.com/blog/keeping-it-clean-washington-d-c-stelcor)

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Bruce Stroyer",
    "url" : "https://www.idealfoundationsystems.com/blog/author/bruce-stroyer"
  },
  "dateModified" : "2025-01-20T18:29:41.068Z",
  "datePublished" : "2016-06-29T14:22:02.000Z",
  "headline" : "STELCOR® DDM For 8-Story Building in Brooklyn",
  "image" : [ "https://www.idealfoundationsystems.com/hubfs/Imported_Blog_Media/211-McGuinness-STELCOR-Case-Study-1-150x150-1.jpg" ],
  "mainEntityOfPage" : {
    "@id" : "https://www.idealfoundationsystems.com/blog/340-stelcor-micropiles-new-8-story-building-brooklyn-ny",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://www.idealfoundationsystems.com/hubfs/ASSETS/logos/Ideal-Logo.png"
    }
  }
}
```